The MBTA expects to shut down parts of the subway on 100 days in 2027, fewer than this year but still enough that more than a quarter of the calendar will see some stretch of track out of service, according to a schedule the agency released Thursday.
The planned outage count is down from 132 days in 2026, 190 in 2025 and 274 in 2024, the MBTA said. Most subway closures are scheduled for weekends. Dates could still shift because of weather or construction needs, and the T said it will post shuttle and alternate-route details ahead of each one.
“Every one day of a track outage is equal to about three months of overnight work,” General Manager Phillip Eng, who is also the interim state transportation secretary, said Thursday, according to the Boston Globe. Eng said the T “may adjust one or two days here and there,” in part because design work for Blue Line repairs and signal upgrades is still coming together.
Green Line: 42 days
The Green Line takes the biggest hit, with 42 planned closure days, the Globe reported. The longest is a nine-day shutdown from Jan. 16 to Jan. 24 between North Station and Babcock Street on the B branch, Kenmore on the C and D branches and Heath Street on the E branch, as crews finish new signals in the central tunnel. The same stretch also closes the weekends of Jan. 9-10, Feb. 6-7, Feb. 20-21 and Feb. 27-28, and for tunnel inspections Sept. 18-19 and Sept. 25-26.
The signal work is meant to prepare the line for the new Type 10 trolleys, which the Globe reported are expected to start carrying passengers in the second half of 2027.
Other Green Line closures include Reservoir to Riverside on the D branch Aug. 21-22 and Aug. 27-30 for Hammond Street Bridge repairs in Newton, and Government Center to East Somerville and Union Square for nine days of track replacement Nov. 13-21. That closure extends to Medford/Tufts on Nov. 13-14 so crews can remove the Broadway Utility Bridge.
Students and other riders along Commonwealth Avenue will lose the B branch between Babcock Street and Boston College on the weekends of Dec. 4-5, Dec. 11-12 and Dec. 18-19, when crews plan to raise platforms eight inches at the branch’s remaining inaccessible above-ground stops, according to the MBTA. Symphony station stays closed for accessibility work, including four new elevators, through spring 2029.
Red and Mattapan lines: 29 days
Red Line closures, including the Mattapan trolley, add up to 29 days, the Globe reported. The longest runs nine days, Aug. 7-15, between JFK/UMass and Braintree for track work and repairs to the Furnace Brook Parkway Bridge in Quincy. JFK/UMass to Quincy Center closes April 8-12 for signal work, and the Red Line closes between Broadway and North Quincy and between Broadway and JFK/UMass on April 24-25.
In Cambridge, the stretch from Alewife to Kendall/MIT closes Jan. 30-31 for tunnel inspections, and Kendall/MIT to JFK/UMass closes the weekends of July 17-18 and July 24-25 for radio upgrades and inspections. Trains will share a single track between Quincy Adams and Braintree on several days in March and April, and between Alewife and Harvard on the weekends of Nov. 6-7 and Nov. 13-14. The Mattapan Line closes March 27-28 and April 3-4 for track work.
Orange and Blue lines
The Orange Line is scheduled for 17 days of closures. The biggest is May 15-23 between North Station and Ruggles for track replacement. Back Bay to Forest Hills closes March 6-7 for tunnel inspections and Ruggles station work, and North Station to Back Bay closes July 10-11 for radio work and Oct. 8-11 so crews can build two accessible transfer elevators at Downtown Crossing.
The Blue Line closes between Bowdoin and Airport for 10 days, June 18-27, for track work, and again Oct. 23-24 for radio upgrades, according to the MBTA.
Commuter rail riders face months of off-peak weekday disruptions on the Needham Line and on the Newburyport Line between Newburyport and Ipswich next spring, plus several weekend changes tied to South Station work and track upgrades at Newtonville on the Worcester Line, Boston.com reported.
How riders see it
Under Eng, the T has chosen longer closures over relying only on nights and weekends, a strategy officials say has cut into a long maintenance backlog, the Globe reported. “Folks on the Orange and Red lines are amazed [by] what they see in terms of improved speed and travel time after shutdowns,” Brian Kane, executive director of the MBTA Advisory Board, told the Globe. “But for some passengers, like on the Green Line, that hasn’t been the experience quite yet.”
Dan Hoeppner, a Green Line rider from Belmont, told the Globe the planned work is “long overdue.” “If you know it’s going to happen in advance, it’s fine,” he said.
Before the new year
The rest of 2026 is not shutdown-free. There is no Red Line service between Broadway and North Quincy this weekend, the Globe reported. Westbound Green Line service from North Station is expected to partly close Dec. 4-7, followed by an eight-day Blue Line closure between Orient Heights and Bowdoin starting Dec. 12. Riders can check current alerts on the MBTA website before they travel.
Sources
- MBTA: MBTA Announces 2027 Construction Schedule with Significantly Fewer Planned Service Outages (Nov. 19, 2026)
- Boston Globe: The MBTA is planning at least 100 days of shutdowns in 2027. Here’s when and where. (Nov. 19, 2026)
- Boston.com: MBTA announces 2027 schedule, promising fewer shutdowns (Nov. 19, 2026)
- Mass Daily News: MBTA plans 100 days of subway shutdowns in 2027, and Green Line riders get hit for 42 of them (Nov. 19, 2026)
- MBTA: Service alerts